(517) 467-6145 e-mail us
- Sample report of a
structural investigation - crane system
RIGID
FRAME & UNDERHUNG CRANE INVESTIGATION
Building
III: Underhung Crane Investigation
Project
Location: Anytown
TABLE
OF CONTENTS
Introduction
II.
Background & History
III.
Crane Loads: Original & Proposed
Changes
IV.
Existing Frame Checks & Results
V.
Proposed Frame Modifications
Option
1: Column & Rafter Coverplating
Option
2: New Support Column Addition
Option
3: Add 3 to Hoist to Existing
VI.
Conclusions
VIl.
References
VIlI.
Appendix
A preliminary
engineering investigation has been undertaken to
arddess the Building III proposed changes for two
underhung cranes as follows: Remove the two 60'
wide three ton underhung cranes in the 70' module
and re-install these two cranes to run on two new
bridge spans of 30' in the same 70' module. (The
existing bridge girders are to be shortened). No
new cranes are added. The two existing side crane
supports will remain and function as the side
supports for the two new locations. Two new
supports are required in the middle portion of
the 70' frame span. Also will consider using one
60' bridge, with 2 - 3 ton hoists. The other 60'
bridge to be removed. NOTE: All engineered
materials and sizes shown in this report are
preliminary and are not intended as a final
design. Specific sizes and quantities called out
in this report are intended for cost estimating,
and to give an idea of what modifications will be
required.
Objectives: To
determine the extent of the structural impact and
effects on the metal building system due to the
change in support locations of two three ton
existing underhung DeMag cranes. To determine the
required structural modifications to the existing
structure so that it can properly support the new
loadings.
II. Background
& History: The building in question is a
pre-engineered metal building manufactured by an
AISC MB certified producer, designed to Metal
Building Manufacturers Association specification.
It is designated as Building III and is a single
slope structure measuring 120' wide by 110' long
having a low eave height of 22' and reaching 25'
at the high eave, resulting in a roof slope of
1/3:12. The primary frames are modular, single
slope rigid frames with spans of 70' and 50\' and
are spaced at 22' on center. Building purlins are
8" deep cold-formed zees at spacings of 5'
-0" on center. The interior frame columns
are built-up columns, with pinned top and bottom
connections. The original rigid frame was
designed for two three-ton underhung cranes to
operate in the 70' aisle in the same bay at the
same time. Please see the attached copy of
manufacturer crane data which pertains to the
existing cranes. Thomas R. Price P.E., of
Structural Solutions LLC met with the owner at
the job site and conducted a visual inspection of
the building on. The purpose of this visit was to
obtain an overall perspective of the existing and
proposed crane changes and to verify randomly
selected sections of the rigid frame. Along with
the field visit, additional information was
obtained from the original crane supplier. The
crane supplier was contacted in order to
thoroughly understand the role of the crane
supplier with regards to the proposed changes.
They provided crane layout rdawings and details
of the planned changes, confirming the proposed
30' and 25' new bridge spans, the reuse of the
existing crane supports, and the locations of the
two new mid-span supports.
III. Original
Crane Loads & Proposed Changes The following
sketch and the information on the following page
represent the pre-engineered metal building
system manufacturer's crane design information
for the original underhung crane systems, showing
the crane loads and load locations. Maximum crane
loads, p1 = 17.19 kips without impact, as per
manufacturer rdawings and calculations which were
provided. The load p2 at the minimum is estimated
to equal approximately 7 kips, which is half the
weight of the bridge plus crane rails, plus a
portion of the trolleys These loads represents
two cranes in the same bay at the same time with
either both cranes on the left side or both
cranes on the right side of the frame.
The following load
cases were considered for the new layout for the
two cranes in the same bay at the same time:
Where p1 = 9.5 kips, p2 = 3 .0 kips The total
crane lateral load is 1.6 kips and was
distributed evenly to each support, equivalent to
0.40 kips per support.
IV. Existing Frame
Checks & Results The pre-engineered metal
building system manufacturer's frame was modeled
and the new crane loadings and locations were
applied. Members 9-12 represent the 70' -0 frame
span which supports the two cranes. Members 13-17
represent the 50'- 0 frame span between columns 2
and 3. Refer to the following page for a graphic
representation of the model. The results clearly
indicate that the new crane loading primarily
overstress all of the rafter members. This was
expected due to the magnitude of the new loads in
combination with their mid-span locations. It is
to be noted that column 2 is also overstressed.
The maximum overstress occurred in member 10
having almost 100% overstress. In addition to the
adverse effects on the members, member
connections including bolts, plates, and welds
will experience design overloading. Frame and
rafter deflections and serviceablity requirements
are also pertinent and minimum allowable values
must be met. Standard metal building rafter
deflections are held to a value equivalent to:
L/180, where L=span in inches. This L/180
deflection represents dead load and live loads
and is not applied to the crane loads. In this
case, the maximum allowable frame deflection
which was held was less than or equal to 1.50
inches at middle of the 70' -0 span. L/180 is
4.67 inches for the 70' -0 module. The new crane
loadings in addition to the code snow loads
resulted in a rafter deflection of 6.5 inches,
greatly exceeding the allowable deflection. Crane
load deflection was also excessive, reaching 2.8
inches.
V. Proposed Frame
Modifications:
Option 1: Build up
the frame members by coverplating the deficient
columns and rafters to improve and substantially
remake their section properties including moments
of inertia, for deflection considerations, their
section modulus along with the compression flange
area to accommodate the significantly increased
bending moments, and web shear stiffeners to deal
with the added shear forces.
Option 2:
Introduce a new interior frame column at a
location between the two new crane supports,
stiffen the existing rafter at the new support
location, and add a foundation to support the new
column loads.
Option 3:
Utilizing one of the existing 60' bridges,
install a second 3 ton hoist on the bridge.
Option 1: Column
and Rafter coverplating: In order to meet
required frame deflections and stresses the
existing rafters will need the following
field-installed materials: NOTE: These sizes for
estimating only - not final. Two 50 ksi hot
rolled angles field welded to the top of the
rafters. One -WT8X38.5 50 ksi hot-rolled tee
section field welded to the bottom flange of the
rafters. Interior column two will need more cross
sectional area to support the added axial loads.
An estimated 20 pounds per lineal foot of
reinforcement will be required. Field welding
will be needed in this operation equivalent to
approximately 48 inches of a 3/16" fillet
weld per linear foot of column. Connection
reinforcements will be required as follows: -
Column1-Rafter 1 knee area will need field
installed diagonal stiffeners. All of the rafter
8-bolt connection plates will need additional
field welds, plate stiffeners and the 3/4 inch
A-325 bolts replaced with A-490 bolts except for
the Rafter1-Rafter 2 connection which will
require major modifications which include plate
and bolt changes. Existing foundations will not
have any significant load increase.
Option 2: Add new
Support Column This option represents a
significant contrast to Option 1 and can be
summarized as follows: Add an interior column
between the two interior crane supports at in the
70' -0 span: TS 6x6x1/4 tube steel, or W8x31 Wide
Flange. Reinforce the rafter at this connection
by adding bearing stiffeners and additional field
welds either side of the support. Reinforce
member 15 in the 50' -0 span with an 8x3/8 bottom
flange cover plate and two hot rolled angles.
Construct new concrete footer for the new column:
5'-0 x 5'-0 x 1'-6. (Assumes allowable soil
bearing to be 3000 psf.). Add new column here.
Option 3: Add 3
ton hoist to existing 60' bridge: For this
option, a second 3 ton hoist is added to one of
the existing 60' bridges. The other existing 60'
bridge is to be removed from service. Provided
that the bridge end truck wheel load is 10,570#
or less, the existing building frames would see
no more load than was considered in the original
building design. Therefore, no building
modifications would be required. The actual wheel
load should be very close to this limit. It would
be the role of the crane supplier to verify this
new wheel load. The existing W16X57 runway beams
must be checked with the new crane data. It is
assumed that this would be up to the crane
supplier, since the beams are part of their
system. 2 - 3 TON HOISTS (ONE BRIDGE)
Vl. Conclusions:
Option 1 (2 bridges, no new column) will require
extensive reinforcment of the building frames,
and may be cost-prohibitave. Each production line
will have its own independant hoist.
Option 2 (2
bridges, add column) will provide the same crane
system as option 1, but with the inconvenience of
a new line of columns in the building. Cost would
likely be less than option 1. Each production
line will have its own independant hoist.
Option 3 (1
bridge, add hoist) will be the simplest of the
three to achieve, but does not provide an
independant hoist to both of the production
lines.
VIl. Referenced
Documents: 1) Mfg. calculations. 2) Mfg.
rdawings.
More information: Structural Engineering
books

Contact
Information
- Telephone:
- (517)
467-6145
- FAX:
- (517)
467-2220
-
- Postal
arddess:
-
- Structural
Solutions LLC
- 8466 Slee
Rd.
- Onsted, MI
49265
- Electronic
mail:
General Information:
Thomas R. Price,
P.E.

[ Home ] [ Engineering Services ] [ Gallery of Projects ] [ Request For Quote ] [ Resources ]
Copyright ©
2007 Structural Solutions LLC, 8466 Slee Rd.
Onsted, MI 49265 Lenawee County
|